Sr. No. | Name ot the Work | Order No. | Amount |
Year of Completion |
Amount of Work Completed Rs. |
1. | Erection, Testing & Commissioning of 220 KV Substation with 220 KV D/C Trasmission line with 3 Nos.80MVA Transformer at Lloyds Steel Ltd. Wardha | Order given by M/s Jyoti Structures | Rs. 16,28,000 | July 1992 | Rs. 16,28,000 |
2. | Erection, Testing & Commissioning of 220KV Main Receiving Substation at Raymond Steels, Nashik | RS/THN/WO/022 | Rs. 7,52,120 | June 1995 | Rs. 7,52,120 |
3. | Erecton of 10MVA, 132/33KV transformer at MSEB Substation, Bramhapuri | EE/SSD/N/T/974 | Rs. 50,000 | June 1995 | Rs. 50,000 |
4. | Erection, Dryout Commissioning of 250MVA, 220/132 KV transformer ar 220KV MSEB Ambazari Substation for BHEL SAS Division, Nagpur | BHE/PUR/SER/AMZ/95001 | Rs. 2,30,000 | December 1995 | Rs. 2,30,000 |
5. | Supply, Construction of Foundation / Control room Erection, Testing, Commissioning of 132/11KV Substation and Transmission Line with 20 MVA transformer alongwith Industrial Electrification Illumination. LT Power and Control Cabling. Telephone and Computer Cabling at Bajaj Plastics Ltd., Nagpur. Accept Transformer & EHV equipments | BDU/PUR/232/06/97-98 | Rs. 96,00,000 | December 1998 | Rs. 94,20,580 |
6. | Erection Testing and Commissioning of 33 KV substation and its associated works at Uniworth Power Ltd., Buttibori |
UPL/SITE/WO and UPL/33 |
Rs. 5,00,000 | January 1996 | Rs. 5,00,000 |
7. | Erection of 100MVA, 220/132 KV transformer Gantry Erection, Stringing etc. at MSEB Substation, Virur |
EE/SSD/N/T/539,540,547 and EE/SSD/N/T/548 |
Rs. 2,30,000 | March 1996 | Rs. 2,30,000 |
8. | Capital Overhauling of 250 MVA, 220/132KV Transformer at MSEB Ambazari Substation for BHEL SAS Division, Nagpur |
BHE/PW/NGP/SURENDRA and SMIR KUMAR/96004 |
Rs. 3,00,000 | May 1996 | Rs. 3,00,000 |
9. | Supply, Erection of 33KV Single Circuit Line for Morarji Brembana Ltd., Buttibori | MBPL/TRL/001 | Rs. 23,53,457 | January 1996 | Rs. 23,53,457 |
10. | Gantry Erection, Stringing. Equipment erection, Dismating and Erection of 25MVA Transformer, erection of 12.5MVA, 25MVA - 3 Nos., 50MVA - 2 Nos., 200MVA transformer alongwith filteration at various MSEB Substation of NAGPUR Division |
EE/SSD/N/T-1269 1244, 2310, 2431, 2528, 2698, 2998, 3027, 329, 464, 615, 711, 698 |
Rs. 6,23,087 | February 1997 | Rs. 6,23,087 |
11. | Designing, Consultancy Liasioning, Approval from MSEB & Electrical Inspectorate for M/s Suryalaxmi Cotton Mills Ltd., Ramtek | — | Rs. 2,75,000 | February 1997 | Rs. 2,75,000 |
12. | Supply, Erection, Testing and Commissioning of 11KV Substation, Factory Illumination, LT Power and Control Cabling, Installation of Machinaries etc. for M/s Grindwell Norton Ltd., Buttibori | PEG/SEAM/N-SITE/033, 34, 35, 36, 37, 38, 889, 895, 896, 906 | Rs. 14,67,877 | March 1997 | Rs. 14,67,877 |
13. | Erection, Testing Commissioning of LT Panels, Electronic weighing System and Computers for M/s Grindwell Norton Ltd., Buttibori | PEG/SEAM/N-SITE/520, 526, 571, 570, 985, 987, 456, 459, 481, 1060, 1133, 1196 | Rs. 3,09,579 | July 1997 | Rs. 3,09,579 |
14. | Erection of Transformer 10 & 25MVA, for MSEB Construction Division, Nagpur | EE/SSD/N/T-793, 2781 | Rs. 66,350 | August 1997 | Rs. 66,350 |
15. | Supply, Laying, Termination, of 33KV XLPE Cable at Khaperkheda and Mankapur, MSEB Substation | EE/SSD/N/Tech/Temd-2/97-98/1659 & 2736 | Rs. 2,55,900 | December 1997 | Rs. 2,55,900 |
16. | Dismantling, Erection and Filteration of 25 MVA transformer 3 Nos. at MSEB Mankapur, Hingna 2 and Pardi substation for Nagpur Urban Zone, Nagpur | NUZ/EE/T-946, 1609, 2085 | Rs. 1,29,320 | December 1997 | Rs. 1,29,320 |
17. | Designing Supply, Erection of 33/0.433 KV sub-station with 2MVA -1 No. and 500 KVA 3 Nos. Transformers with allied equipments |
SP/PO/CAP/33/96-97/0983 Dt. 13-11-1996 |
Rs. 27,53,000 | December 1997 | Rs. 27,53,000 |
18. | Laying of Earth Pits at 132KV MSEB Mansar Substation | EE/SSD/N/T/1783 | Rs. 40,000 | December 1997 | Rs. 40,000 |
19. | Supply, Photo, Wiring of GEC Alsthom make realys at 220KV MSEB Virur Substation | EE/SSD/N/T/2702, 28142823 | Rs. 63,097 | January 1998 | Rs. 63,097 |
20. | Excavation, Stubsetting, erection, stringing of Tower for reorientation of 220KV Khaperkheda - Ambazari 1 Line for EHVT Lines Division, Nagpur |
EE/EHVT/DN/NGP/T-2/Tender - 6/AU28/97-98/3226 |
Rs. 4,08,810 | February 1998 | Rs. 4,08,810 |
21. | Supply, Erection, Testing & Commissioning of 33KV Substation & Transmission line for M/s Surbalaxmi Cotton Mills Ltd., Ramtek | SL/CML/NGP/113, 366 | Rs. 15,54,524 | March 1998 | Rs. 15,54,524 |
22. | Supply, Fabrication, Erectiion, Foundation of 18 mtr high lighting towers at MSEB Khaperkheda Thermal Power Station |
SE/GP/KPKD/LT/U3 and 4/97-98/58/91 |
Rs. 1,77,000 | March 1998 | Rs. 1,77,000 |
23. | Capital Overhauling of 250MVA, 220/132KV Transformer at MSEB Ambazari Substation for BHEL SAS Division, Nagpur | PW/NGP/PUR/SER/97/31 | Rs. 4,73,500 | April 1998 | Rs. 4,73,500 |
24. | Filteration of transformers of 25MVA at MSEB Mouda Substation | EE/SSD/N/T/527, 787 | Rs. 69,200 | April 1998 | Rs. 69,200 |
25. | Rectification of 250MVA, 220/132KV Transformer bushings at MSEB Ambazari Substation for BHEL SAS Division, Nagpur | PW/NGP/PUR/SER/98/04 | Rs. 1,35,000 | June 1998 | Rs. 1,35,000 |
26. | Supply,Fabrication, Erection, Foundation of 18 mtr high lighting towers at MSEB Khaperkheda Thermal Power station | DYCE(GEN)/KPKD/LT/98-99/26/763 | Rs. 1,84,500 | September 1998 | Rs. 1,84,500 |
27. | Designing, Erection, Testing & Commissioning of 11KV Substation, Factory Illustration & LT Panels, LT Power Cabling etc. at M/s Castwell Industries, Nagpur | CAST/98-99/050 | Rs. 15,50,000 | October 1998 | Rs. 15,50,000 |
28. | Electrical Installation & Commission of Tunnel Kiln & Machinaries at Grindwell Norton LTD., Buttibori | PEG/SEAM/N-S/1302,073376378379 | Rs. 87,492 | November 1998 | Rs. 87,492 |
29. | Erection of 33KV Double circuit line from Pardi to Nagpur water Seawge Plant for MSEB Nagpur Urban Zone | CE/NUZ/Tech/26/561 | Rs. 2,00,000 | January 1999 | Rs. 3,00,000 |
30. | M/s Hindustan Constructioin Company Ltd., Mumbai for Gosikhurd Dam Project, Desiging, Supply, Erection,Testing & Commissioning of 2.5 MVA 33/11KV Sub-Stn. & 11/0.4 KV Sub-Stn. With Dif. Rating 8 No. Transformers Incl. Civil Work, Illumination System for offices & Colony etc. Liasioning with MSEB & Electrical Inspectorate. etc. |
HCL/EL/GSW/113HCGP/ 419HCGP/EL420HCGL/ 686HCGP/1212HCGP/ EL/0085HCGP/EL/ 0212HCGP/EL/926 |
Rs. 91,48,693 | February 1999 | Rs. 91,48,693 |
31. | M/s BHEL SAS Division, Nagpur, Shifting, Repair & Overhauling of 150MVA GT, Transformer at MSEB, Koradi Thermal Power Station | PW/NGP/PUR/SER/98/30 | Rs. 5,91,000 | February 1999 | Rs. 5,91,000 |
32. | M/s LARSEN & TOUBRO LTD. Mumbai. Electrical Works for Indian Oil Corp. Ltd. Ratail Outlests at Takli & Purna. Dist.- Parbhani |
L.O.I. - Date 27-3-2000 L.O.I. - Date 01-06-2000 |
Rs. 2,59,136 | July 2000 | Rs. 2,59,136 |
33. | M/s Bajaj Dhatu Udyog MIDC, Nagpur, Installation, Testing & Commission of 132KV Transformer Bay with Civil foundation, development of Land, Earthmat and allied Electrical works as per drawings |
BDU/PUR-232/452/99-2000 Dt. 26-04-99 |
Rs. 78,60,000 | 2000 | Rs. 78,60,000 |
34. | M/s LARSEN & TOUBRO., Mumbai, Electrical Works for Indian Oil Corp. Ltd. 2 No. Retail Outlest at Dist - Parbhani | L.O.I.- Dt. 27-03-2000 | Rs. 5,89,419 | February 2001 | Rs. 5,89,419 |
35. | M/s LARSEN & TOUBRO LTD. ECC Construction Group, L & T Hyderabad Regional Office, Hyderabad. Work of Internal Electrification for Garrison Engineers, MES. Kamptee |
HCHG1473-384820 Dt.10-04-2000 |
Rs. 12,00,000 | December 2001 | Rs. 12,00,000 |
36. | MSEB S.E. EHV. Const. Circle, Nagpur Work of Excavation,stub-setting,Erection of Towers and stringing etc. of 132 kV Pusad-Umarkhed Line 40.81 Kms |
SE/CC/NGP/T-3/Tender-12/99-2000/2744 Dt.24-11.1999 |
Rs. 67,09,646 | March 2002 | Rs. 67,09,646 |
37. | M/s Dinshaw's Dairy Foods Ltd, MIDC, Butibori, Nagpur - 33 kV Substation and Cable Laying,Street Lighting, Internal Electrification, LAN/Telephone cable.etc. |
DDF/PROJ/PO-16/33/47 Dt.6-1-2001 & 28-4-2001 |
Rs. 30,42,500 | March 2002 | Rs. 30,42,500 |
38. | Executive Engineer North Mumbai Electrical Division, P.W.D. Mulund West, Mumbai - 400080 - 11 kV HT Line with Transformer Substation & Service Line to Gujrat Earthquake rehabilitation of village Adhoi, Tah. Bacchau,Dist. Bhuj, Gujrat (Turn-key) |
EE/NMED/TC-47&48 2001-02 Dt.11-01-2002 |
Rs. 16,61,392 | May 2002 | Rs. 16,61,392 |
39. | MSEB S.E. EHV. Const. Circle, Nagpur - Work of Excavation,stub-setting,Erection of Towers and stringing etc. of 132 kV Malegaon - Washim Line.14.89 Kms |
CE/EHV/T/2000/01/677 Dt.17-03-2001 |
Rs. 59,84,375 | March 2003 | Rs. 59,84,375 |
40. | MSEB S.E. EHV. Const. Circle, Nagpur - Work of Excavation,stub-setting,Erection of Towers and stringing etc. of 132 kV Mul - Sindewahi Line.30 Kms. |
SE/CC/NGP/T-3/Tender-10/2002-03/347 Dt.09-02.2004 |
1,15,87,730 | March 2005 | 1,16,15,590 |
41. | MSEB S.E. EHV. Const. Circle, Nagpur - Work of Excavation,stub-setting,Erection of Towers and stringing etc. of 132 kV Durgwada - Daryapur Line.17.564 Kms. |
SE/CC/NGP/T-3/Tender-9/2003-04/716 Dt.26-03.2004 |
Rs. 66,20,424 | February 2005 | Rs. 60,78,050 |
42. | MSEB S.E. EHV. Const. Circle, Nagpur - Work of Excavation,stub-setting,Erection of Towers and stringing etc. of 220 kV ROW work for Kanhan - Umred Line | SE/CC/NGP/T-4/Tender-1/2006-07/446 & 447 Dt.26-03.2004 | Rs. 46,20,873 | ||
43. | MSETCL S.E. EHV. Const. Circle, Nagpur - Work of Restoration of collapsed line Erection of Towers and stringing etc. of 220 kV work for Kanhan - Sunflag Bhandara Line on war footing basis with Kanhan River Crossing | SE/CC/T-4/BRDN/2101 Dt.03-SEP.2007 | Rs. 2,85,400 | 10 Days | |
44. | MSEB C.E, Amravati Zone, Akola - Turnkey work of 33/11 KV- 5MVA Sub-Station with Complete Civil work and 33 KV O/H line at Vidhyut Bhavan Amravati | LOA Dt:-16.09.2003 | 1,02,64,000 | March 2005 | |
45. | MSETCL-S.E, HVDC Chandrapur Circle, Chandrapur - Turnkey Contract work of Shifting of 33 KV Earth Electrod line at CTPS Durgapur Dist.Chandrapur |
SE/HVDC/RS/O&M/ Circle/CHND/Tech/2689 Dt:- 06 SEP 2006 |
Rs. 85,41,956 | ||
46. | MAHAGENCO - Turnkey Contract work of Shifting of 33 KV line on 132KV D/C Tower at TPS, Bhusawal Dist.Jalgaon | BTPS/CGM/TECH/PUR/T-93/2007/1752 Dated 18/02/2008. | Rs. 87,83,296 | December 2008 | Rs. 98,00,000 |
47. | MSEDCL C.E Kalyan Zone, Kalyan - Turnkey work of 22/.433 KV- 315,500,630 KVA DTC/ HT Line & HT Cable with Complete Civil work at Ulhasnagar & Dombivali - Joint Venture with M/S. Sunil Hi Tech Engineers Ltd. Nagpur |
SHEL/NGP/APDRP/ Kalyan/1580 Dated 06/07/2007. |
17,00,00,000 | January 2009 | |
48. | MSEDCL C.E, Nagpur Zone, Nagpur - Turnkey Contract work of 33/11 KV- 5MVA & 10 MVA Sub-Station with Complete Civil work and 11 KV O/H line at Dist.Chandrapur - Joint Venture with M/S. Sunil Hi Tech Engineers Ltd.Nagpur | Shel/Ngp/Chandrapur-BL/WO/3059 Dated 15/07/2007 | Rs. 16,00,00,000 | January 2009 | |
49. | Supply Erection of HT/LT lines, internal Electrification work at Bajaj steel Industries Ltd, C-108 MIDC, Nagpur | BSIL/C-108/MIDC/Nagpur | Rs. 60,00,000 | January 2009 | |
50. | Work on turn key basis for shifting of 2nos 33KV sootgirni feeder from 220KV Sub Station | SE/NRC/NGP/TECH/941 | Rs. 16,53,638 | January 2009 | |
51. | Establishing of 22/11 KV 2x10 MVA Sub-Stn. at Raheja, Eternity, Film city, Khidkali on Turn Key Basis for MSEDCL, Bhandup Zone, Mumbai. The Joint Venture with M/S. Sunil Hi Tech Engineers Ltd.Nagpur | CE/BNDUZ/INFRA/T-607 Dated 15/04/2008. | Rs. 24,75,78,000 | January 2010 | |
52. | Work of Commissioning of L T Line for electrification of additional street lights under various scheme in Bhiwapur/Umred/Kuhi Sub Division under Division No 1, for MSEDCL, Nagpur | EE-1/NGP/Tech/08-09/1221/1218/1216/1222. Dated 24/02/2009. | Rs. 70,00,000 | April 2009 | |
53. | Fixing and Tightening of Caps of Quadruple Spacers, Dampers on Pole-I & Pole-II from Loc. 386 to 681of 500KV Chandrapur- Padghe HVDC Line for MAHATRANSCO. |
EE/HVDC/TL/O&M/ Dn./DRP/Tech/438 Dated 30/03/2009 |
Rs. 11,49,910 | September 2009 | |
54. | Work on turn key basis for Energisation of Agricultural Pumps in Nagpur Sub Division no 1 | SE/NRC/NGP/Tech/09-10/T-17/2317. Dated 31/03/10 | Rs. 50,00,000 | June 2010 | |
55. | Supply, Erection, Testing, Commissioning & Consultancy of 132 KV 4 KMS Line from 220 KV MIDC, Gadchiroli Sub-Station to M/S. Vayunandana Power Ltd. Plant at Village Kaneri, Mul Road, Dist.-Gadchiroli | VPL/PO/HTA/87/09-10 Dt.13/05/2009 & VPL/PO/HTA/88/09-19 Dt.15/05/2009 | Rs. 1,14,00,000 | March 2010 | |
56. | Supply, Erection, Testing & Commissioning of 220 KV 17 KMS line from 220 KV Umred Sub-Station to M/S. Shree Virangana Steels Ltd.Power Plant at Village Heti,Mouza Ukarwahi, Tal. Umred, Dist.- Nagpur | SVSL/NGP/W-CPP/HTA/09-10/39 Dt. 21/08/2009 | Rs. 2,52,15,650 | December 2010 | |
57. | Partial Turnkey work for construction of 132 KV DC line fromM/s GSEPL plantto 132 KV Subsstation3.5 KMs |
SHEL/NGP/ELEC/ GSEPL/2008-09/ 10502 (A-1) Dt. 14/02/2009 |
Rs. 2,37,52,000 | October 2010 | |
58. | Consultancy of Electrical work of 91.5 x 6 MW Hydro Power Project at Sudan, for Afcons Infrastructure Limited | AFCONS/HTA/10-11/189 | Rs. 2,50,000 | December 2010 | Rs. 2,50,000 |
59. | On Turnkey Basis Supply and Erection of 11 KV Transmission line for Power Evacuation of 2x2 MWP Solar Power Plant at Katol, Nagpur | CREL/SOLAR/11KV/001 Dated 13/09/2011 | Rs. 1,43,87,631 | November 2011 | Rs. 1,60,00,000 |
60. | Establishing of 22/11 KV 2x10 MVA Sub-Stn. at Raheja, Eternity, Film city, Khidkali on Turn Key Basis for MSEDCL, Bhandup Zone, Mumbai. The Joint Venture with M/S. Sunil Hi Tech Engineers Ltd. Nagpur | CE/BNDUZ/INFRA/T-607 Dated 15/04/2008 | Rs. 24,75,78,000 | August 2012 | Rs. 24,75,78,000 |
61. | Supply, Erection, Testing & Commissioning of 33 KV Breaker with Transformer bay for Augumentation of 2 MVA Transformer at Grindwell Norton Limited Butibori |
P. O. No. 111/7406996/0, 00005/7406662/0, WO/PRJ/1847/02 Dated 17/11/2011 |
Rs. 44,87,403 | August 2012 | Rs. 44,87,403 |
62. | Consultancy of 220 KV Line & 220 KV Substation at M/S. Suryalakshmi Cotton Mills Ltd.Power Plant at Village Nagardhan, Tal. Ramtek, Dist.- Nagpur | SLCML/HTA/C/10-11/45 Dt. 24/08/2010 | 2% of Total Electrical Installations in line and Sub-Station | February 2013 | 2% of Total Electrical Installations in line and Sub-Station |
63. | Turnkey Contract of Supply and Erection of 220 KV Double Circuit Tower Line 4 Kms. from Suryalakshmi Cotton Mills Ltd, Nagardhan, Ramtek, Nagpur | SCML/HTA/LOI Dated 06/09/2011 | Rs. 2,25,00,000 | February 2013 | Rs. 2,25,00,000 |
64. | Turnkey Contract of Supply and Erection of 33 KV Pin type Line 10 Kms. & Bay at 33/11KV Umari S/Stn to Site at Khursapar, Tah. Saoner, Dist.Nagpur.for Maharashtra Border Check Post Network Limited | MBCPNL/HTA/11-12/883 Dated 13/12/2011 | Rs. 1,05,78,787 | December 2012 | Rs. 1,05,78,787 |
65. | Work order for Supply Erection & Commissioning of additional LT Lines & Diesel Generator at Sawner BCP. For Maharashtra Border Check Post Network Limited |
MBCPNL/HTA/BPC /ELE/WO/12-13/1535 Dated 28/05/2012 |
Rs. 5,92,910 | December 2012 | Rs. 5,92,910 |
66. | Work order for Supply Erection & Commissioning of additional 33 KV HT line & 33 KV DP Structure with GOD, DO, & LA. at Sawner BCP. For Maharashtra Border Check Post Network Limited |
MBCPNL/HTA/BPC/ ELE/WO/12-13/1938 Dated 01/11/2012 |
Rs. 12,28,980 | December 2012 | Rs. 12,28,980 |