Our Projects

Sr. No. Name ot the Work Order No. Amount Year of
Completion
Amount of Work
Completed Rs.
1. Erection, Testing & Commissioning of 220 KV Substation with 220 KV D/C Trasmission line with 3 Nos.80MVA Transformer at Lloyds Steel Ltd. Wardha Order given by M/s Jyoti Structures Rs. 16,28,000 July 1992 Rs. 16,28,000
2. Erection, Testing & Commissioning of 220KV Main Receiving Substation at Raymond Steels, Nashik RS/THN/WO/022 Rs. 7,52,120 June 1995 Rs. 7,52,120
3. Erecton of 10MVA, 132/33KV transformer at MSEB Substation, Bramhapuri EE/SSD/N/T/974 Rs. 50,000 June 1995 Rs. 50,000
4. Erection, Dryout Commissioning of 250MVA, 220/132 KV transformer ar 220KV MSEB Ambazari Substation for BHEL SAS Division, Nagpur BHE/PUR/SER/AMZ/95001 Rs. 2,30,000 December 1995 Rs. 2,30,000
5. Supply, Construction of Foundation / Control room Erection, Testing, Commissioning of 132/11KV Substation and Transmission Line with 20 MVA transformer alongwith Industrial Electrification Illumination. LT Power and Control Cabling. Telephone and Computer Cabling at Bajaj Plastics Ltd., Nagpur. Accept Transformer & EHV equipments BDU/PUR/232/06/97-98 Rs. 96,00,000 December 1998 Rs. 94,20,580
6. Erection Testing and Commissioning of 33 KV substation and its associated works at Uniworth Power Ltd., Buttibori UPL/SITE/WO
and UPL/33
Rs. 5,00,000 January 1996 Rs. 5,00,000
7. Erection of 100MVA, 220/132 KV transformer Gantry Erection, Stringing etc. at MSEB Substation, Virur EE/SSD/N/T/539,540,547
and EE/SSD/N/T/548
Rs. 2,30,000 March 1996 Rs. 2,30,000
8. Capital Overhauling of 250 MVA, 220/132KV Transformer at MSEB Ambazari Substation for BHEL SAS Division, Nagpur BHE/PW/NGP/SURENDRA
and SMIR KUMAR/96004
Rs. 3,00,000 May 1996 Rs. 3,00,000
9. Supply, Erection of 33KV Single Circuit Line for Morarji Brembana Ltd., Buttibori MBPL/TRL/001 Rs. 23,53,457 January 1996 Rs. 23,53,457
10. Gantry Erection, Stringing. Equipment erection, Dismating and Erection of 25MVA Transformer, erection of 12.5MVA, 25MVA - 3 Nos., 50MVA - 2 Nos., 200MVA transformer alongwith filteration at various MSEB Substation of NAGPUR Division EE/SSD/N/T-1269
1244, 2310, 2431, 2528, 2698, 2998, 3027, 329, 464, 615, 711, 698
Rs. 6,23,087 February 1997 Rs. 6,23,087
11. Designing, Consultancy Liasioning, Approval from MSEB & Electrical Inspectorate for M/s Suryalaxmi Cotton Mills Ltd., Ramtek Rs. 2,75,000 February 1997 Rs. 2,75,000
12. Supply, Erection, Testing and Commissioning of 11KV Substation, Factory Illumination, LT Power and Control Cabling, Installation of Machinaries etc. for M/s Grindwell Norton Ltd., Buttibori PEG/SEAM/N-SITE/033, 34, 35, 36, 37, 38, 889, 895, 896, 906 Rs. 14,67,877 March 1997 Rs. 14,67,877
13. Erection, Testing Commissioning of LT Panels, Electronic weighing System and Computers for M/s Grindwell Norton Ltd., Buttibori PEG/SEAM/N-SITE/520, 526, 571, 570, 985, 987, 456, 459, 481, 1060, 1133, 1196 Rs. 3,09,579 July 1997 Rs. 3,09,579
14. Erection of Transformer 10 & 25MVA, for MSEB Construction Division, Nagpur EE/SSD/N/T-793, 2781 Rs. 66,350 August 1997 Rs. 66,350
15. Supply, Laying, Termination, of 33KV XLPE Cable at Khaperkheda and Mankapur, MSEB Substation EE/SSD/N/Tech/Temd-2/97-98/1659 & 2736 Rs. 2,55,900 December 1997 Rs. 2,55,900
16. Dismantling, Erection and Filteration of 25 MVA transformer 3 Nos. at MSEB Mankapur, Hingna 2 and Pardi substation for Nagpur Urban Zone, Nagpur NUZ/EE/T-946, 1609, 2085 Rs. 1,29,320 December 1997 Rs. 1,29,320
17. Designing Supply, Erection of 33/0.433 KV sub-station with 2MVA -1 No. and 500 KVA 3 Nos. Transformers with allied equipments SP/PO/CAP/33/96-97/0983
Dt. 13-11-1996
Rs. 27,53,000 December 1997 Rs. 27,53,000
18. Laying of Earth Pits at 132KV MSEB Mansar Substation EE/SSD/N/T/1783 Rs. 40,000 December 1997 Rs. 40,000
19. Supply, Photo, Wiring of GEC Alsthom make realys at 220KV MSEB Virur Substation EE/SSD/N/T/2702, 28142823 Rs. 63,097 January 1998 Rs. 63,097
20. Excavation, Stubsetting, erection, stringing of Tower for reorientation of 220KV Khaperkheda - Ambazari 1 Line for EHVT Lines Division, Nagpur EE/EHVT/DN/NGP/T-2/Tender -
6/AU28/97-98/3226
Rs. 4,08,810 February 1998 Rs. 4,08,810
21. Supply, Erection, Testing & Commissioning of 33KV Substation & Transmission line for M/s Surbalaxmi Cotton Mills Ltd., Ramtek SL/CML/NGP/113, 366 Rs. 15,54,524 March 1998 Rs. 15,54,524
22. Supply, Fabrication, Erectiion, Foundation of 18 mtr high lighting towers at MSEB Khaperkheda Thermal Power Station SE/GP/KPKD/LT/U3
and 4/97-98/58/91
Rs. 1,77,000 March 1998 Rs. 1,77,000
23. Capital Overhauling of 250MVA, 220/132KV Transformer at MSEB Ambazari Substation for BHEL SAS Division, Nagpur PW/NGP/PUR/SER/97/31 Rs. 4,73,500 April 1998 Rs. 4,73,500
24. Filteration of transformers of 25MVA at MSEB Mouda Substation EE/SSD/N/T/527, 787 Rs. 69,200 April 1998 Rs. 69,200
25. Rectification of 250MVA, 220/132KV Transformer bushings at MSEB Ambazari Substation for BHEL SAS Division, Nagpur PW/NGP/PUR/SER/98/04 Rs. 1,35,000 June 1998 Rs. 1,35,000
26. Supply,Fabrication, Erection, Foundation of 18 mtr high lighting towers at MSEB Khaperkheda Thermal Power station DYCE(GEN)/KPKD/LT/98-99/26/763 Rs. 1,84,500 September 1998 Rs. 1,84,500
27. Designing, Erection, Testing & Commissioning of 11KV Substation, Factory Illustration & LT Panels, LT Power Cabling etc. at M/s Castwell Industries, Nagpur CAST/98-99/050 Rs. 15,50,000 October 1998 Rs. 15,50,000
28. Electrical Installation & Commission of Tunnel Kiln & Machinaries at Grindwell Norton LTD., Buttibori PEG/SEAM/N-S/1302,073376378379 Rs. 87,492 November 1998 Rs. 87,492
29. Erection of 33KV Double circuit line from Pardi to Nagpur water Seawge Plant for MSEB Nagpur Urban Zone CE/NUZ/Tech/26/561 Rs. 2,00,000 January 1999 Rs. 3,00,000
30. M/s Hindustan Constructioin Company Ltd., Mumbai for Gosikhurd Dam Project, Desiging, Supply, Erection,Testing & Commissioning of 2.5 MVA 33/11KV Sub-Stn. & 11/0.4 KV Sub-Stn. With Dif. Rating 8 No. Transformers Incl. Civil Work, Illumination System for offices & Colony etc. Liasioning with MSEB & Electrical Inspectorate. etc. HCL/EL/GSW/113HCGP/
419HCGP/EL420HCGL/
686HCGP/1212HCGP/
EL/0085HCGP/EL/
0212HCGP/EL/926
Rs. 91,48,693 February 1999 Rs. 91,48,693
31. M/s BHEL SAS Division, Nagpur, Shifting, Repair & Overhauling of 150MVA GT, Transformer at MSEB, Koradi Thermal Power Station PW/NGP/PUR/SER/98/30 Rs. 5,91,000 February 1999 Rs. 5,91,000
32. M/s LARSEN & TOUBRO LTD. Mumbai. Electrical Works for Indian Oil Corp. Ltd. Ratail Outlests at Takli & Purna. Dist.- Parbhani L.O.I. - Date 27-3-2000
L.O.I. - Date 01-06-2000
Rs. 2,59,136 July 2000 Rs. 2,59,136
33. M/s Bajaj Dhatu Udyog MIDC, Nagpur, Installation, Testing & Commission of 132KV Transformer Bay with Civil foundation, development of Land, Earthmat and allied Electrical works as per drawings BDU/PUR-232/452/99-2000
Dt. 26-04-99
Rs. 78,60,000 2000 Rs. 78,60,000
34. M/s LARSEN & TOUBRO., Mumbai, Electrical Works for Indian Oil Corp. Ltd. 2 No. Retail Outlest at Dist - Parbhani L.O.I.- Dt. 27-03-2000 Rs. 5,89,419 February 2001 Rs. 5,89,419
35. M/s LARSEN & TOUBRO LTD. ECC Construction Group, L & T Hyderabad Regional Office, Hyderabad. Work of Internal Electrification for Garrison Engineers, MES. Kamptee HCHG1473-384820
Dt.10-04-2000
Rs. 12,00,000 December 2001 Rs. 12,00,000
36. MSEB S.E. EHV. Const. Circle, Nagpur Work of Excavation,stub-setting,Erection of Towers and stringing etc. of 132 kV Pusad-Umarkhed Line 40.81 Kms SE/CC/NGP/T-3/Tender-12/99-2000/2744
Dt.24-11.1999
Rs. 67,09,646 March 2002 Rs. 67,09,646
37. M/s Dinshaw's Dairy Foods Ltd, MIDC, Butibori, Nagpur - 33 kV Substation and Cable Laying,Street Lighting, Internal Electrification, LAN/Telephone cable.etc. DDF/PROJ/PO-16/33/47
Dt.6-1-2001 & 28-4-2001
Rs. 30,42,500 March 2002 Rs. 30,42,500
38. Executive Engineer North Mumbai Electrical Division, P.W.D. Mulund West, Mumbai - 400080 - 11 kV HT Line with Transformer Substation & Service Line to Gujrat Earthquake rehabilitation of village Adhoi, Tah. Bacchau,Dist. Bhuj, Gujrat (Turn-key) EE/NMED/TC-47&48
2001-02 Dt.11-01-2002
Rs. 16,61,392 May 2002 Rs. 16,61,392
39. MSEB S.E. EHV. Const. Circle, Nagpur - Work of Excavation,stub-setting,Erection of Towers and stringing etc. of 132 kV Malegaon - Washim Line.14.89 Kms CE/EHV/T/2000/01/677
Dt.17-03-2001
Rs. 59,84,375 March 2003 Rs. 59,84,375
40. MSEB S.E. EHV. Const. Circle, Nagpur - Work of Excavation,stub-setting,Erection of Towers and stringing etc. of 132 kV Mul - Sindewahi Line.30 Kms. SE/CC/NGP/T-3/Tender-10/2002-03/347
Dt.09-02.2004
1,15,87,730 March 2005 1,16,15,590
41. MSEB S.E. EHV. Const. Circle, Nagpur - Work of Excavation,stub-setting,Erection of Towers and stringing etc. of 132 kV Durgwada - Daryapur Line.17.564 Kms. SE/CC/NGP/T-3/Tender-9/2003-04/716
Dt.26-03.2004
Rs. 66,20,424 February 2005 Rs. 60,78,050
42. MSEB S.E. EHV. Const. Circle, Nagpur - Work of Excavation,stub-setting,Erection of Towers and stringing etc. of 220 kV ROW work for Kanhan - Umred Line SE/CC/NGP/T-4/Tender-1/2006-07/446 & 447 Dt.26-03.2004 Rs. 46,20,873    
43. MSETCL S.E. EHV. Const. Circle, Nagpur - Work of Restoration of collapsed line Erection of Towers and stringing etc. of 220 kV work for Kanhan - Sunflag Bhandara Line on war footing basis with Kanhan River Crossing SE/CC/T-4/BRDN/2101 Dt.03-SEP.2007 Rs. 2,85,400 10 Days  
44. MSEB C.E, Amravati Zone, Akola - Turnkey work of 33/11 KV- 5MVA Sub-Station with Complete Civil work and 33 KV O/H line at Vidhyut Bhavan Amravati LOA Dt:-16.09.2003 1,02,64,000 March 2005  
45. MSETCL-S.E, HVDC Chandrapur Circle, Chandrapur - Turnkey Contract work of Shifting of 33 KV Earth Electrod line at CTPS Durgapur Dist.Chandrapur SE/HVDC/RS/O&M/
Circle/CHND/Tech/2689
Dt:- 06 SEP 2006
Rs. 85,41,956    
46. MAHAGENCO - Turnkey Contract work of Shifting of 33 KV line on 132KV D/C Tower at TPS, Bhusawal Dist.Jalgaon BTPS/CGM/TECH/PUR/T-93/2007/1752 Dated 18/02/2008. Rs. 87,83,296 December 2008 Rs. 98,00,000
47. MSEDCL C.E Kalyan Zone, Kalyan - Turnkey work of 22/.433 KV- 315,500,630 KVA DTC/ HT Line & HT Cable with Complete Civil work at Ulhasnagar & Dombivali - Joint Venture with M/S. Sunil Hi Tech Engineers Ltd. Nagpur SHEL/NGP/APDRP/
Kalyan/1580
Dated 06/07/2007.
17,00,00,000 January 2009  
48. MSEDCL C.E, Nagpur Zone, Nagpur - Turnkey Contract work of 33/11 KV- 5MVA & 10 MVA Sub-Station with Complete Civil work and 11 KV O/H line at Dist.Chandrapur - Joint Venture with M/S. Sunil Hi Tech Engineers Ltd.Nagpur Shel/Ngp/Chandrapur-BL/WO/3059 Dated 15/07/2007 Rs. 16,00,00,000 January 2009  
49. Supply Erection of HT/LT lines, internal Electrification work at Bajaj steel Industries Ltd, C-108 MIDC, Nagpur BSIL/C-108/MIDC/Nagpur Rs. 60,00,000 January 2009  
50. Work on turn key basis for shifting of 2nos 33KV sootgirni feeder from 220KV Sub Station SE/NRC/NGP/TECH/941 Rs. 16,53,638 January 2009  
51. Establishing of 22/11 KV 2x10 MVA Sub-Stn. at Raheja, Eternity, Film city, Khidkali on Turn Key Basis for MSEDCL, Bhandup Zone, Mumbai. The Joint Venture with M/S. Sunil Hi Tech Engineers Ltd.Nagpur CE/BNDUZ/INFRA/T-607 Dated 15/04/2008. Rs. 24,75,78,000 January 2010  
52. Work of Commissioning of L T Line for electrification of additional street lights under various scheme in Bhiwapur/Umred/Kuhi Sub Division under Division No 1, for MSEDCL, Nagpur EE-1/NGP/Tech/08-09/1221/1218/1216/1222. Dated 24/02/2009. Rs. 70,00,000 April 2009  
53. Fixing and Tightening of Caps of Quadruple Spacers, Dampers on Pole-I & Pole-II from Loc. 386 to 681of 500KV Chandrapur- Padghe HVDC Line for MAHATRANSCO. EE/HVDC/TL/O&M/
Dn./DRP/Tech/438
Dated 30/03/2009
Rs. 11,49,910 September 2009  
54. Work on turn key basis for Energisation of Agricultural Pumps in Nagpur Sub Division no 1 SE/NRC/NGP/Tech/09-10/T-17/2317. Dated 31/03/10 Rs. 50,00,000 June 2010  
55. Supply, Erection, Testing, Commissioning & Consultancy of 132 KV 4 KMS Line from 220 KV MIDC, Gadchiroli Sub-Station to M/S. Vayunandana Power Ltd. Plant at Village Kaneri, Mul Road, Dist.-Gadchiroli VPL/PO/HTA/87/09-10 Dt.13/05/2009 & VPL/PO/HTA/88/09-19 Dt.15/05/2009 Rs. 1,14,00,000 March 2010  
56. Supply, Erection, Testing & Commissioning of 220 KV 17 KMS line from 220 KV Umred Sub-Station to M/S. Shree Virangana Steels Ltd.Power Plant at Village Heti,Mouza Ukarwahi, Tal. Umred, Dist.- Nagpur SVSL/NGP/W-CPP/HTA/09-10/39 Dt. 21/08/2009 Rs. 2,52,15,650 December 2010  
57. Partial Turnkey work for construction of 132 KV DC line fromM/s GSEPL plantto 132 KV Subsstation3.5 KMs SHEL/NGP/ELEC/
GSEPL/2008-09/
10502 (A-1) Dt. 14/02/2009
Rs. 2,37,52,000 October 2010  
58. Consultancy of Electrical work of 91.5 x 6 MW Hydro Power Project at Sudan, for Afcons Infrastructure Limited AFCONS/HTA/10-11/189 Rs. 2,50,000 December 2010 Rs. 2,50,000
59. On Turnkey Basis Supply and Erection of 11 KV Transmission line for Power Evacuation of 2x2 MWP Solar Power Plant at Katol, Nagpur CREL/SOLAR/11KV/001 Dated 13/09/2011 Rs. 1,43,87,631 November 2011 Rs. 1,60,00,000
60. Establishing of 22/11 KV 2x10 MVA Sub-Stn. at Raheja, Eternity, Film city, Khidkali on Turn Key Basis for MSEDCL, Bhandup Zone, Mumbai. The Joint Venture with M/S. Sunil Hi Tech Engineers Ltd. Nagpur CE/BNDUZ/INFRA/T-607 Dated 15/04/2008 Rs. 24,75,78,000 August 2012 Rs. 24,75,78,000
61. Supply, Erection, Testing & Commissioning of 33 KV Breaker with Transformer bay for Augumentation of 2 MVA Transformer at Grindwell Norton Limited Butibori P. O. No. 111/7406996/0,
00005/7406662/0,
WO/PRJ/1847/02
Dated 17/11/2011
Rs. 44,87,403 August 2012 Rs. 44,87,403
62. Consultancy of 220 KV Line & 220 KV Substation at M/S. Suryalakshmi Cotton Mills Ltd.Power Plant at Village Nagardhan, Tal. Ramtek, Dist.- Nagpur SLCML/HTA/C/10-11/45 Dt. 24/08/2010 2% of Total Electrical Installations in line and Sub-Station February 2013 2% of Total Electrical Installations in line and Sub-Station
63. Turnkey Contract of Supply and Erection of 220 KV Double Circuit Tower Line 4 Kms. from Suryalakshmi Cotton Mills Ltd, Nagardhan, Ramtek, Nagpur SCML/HTA/LOI Dated 06/09/2011 Rs. 2,25,00,000 February 2013 Rs. 2,25,00,000
64. Turnkey Contract of Supply and Erection of 33 KV Pin type Line 10 Kms. & Bay at 33/11KV Umari S/Stn to Site at Khursapar, Tah. Saoner, Dist.Nagpur.for Maharashtra Border Check Post Network Limited MBCPNL/HTA/11-12/883 Dated 13/12/2011 Rs. 1,05,78,787 December 2012 Rs. 1,05,78,787
65. Work order for Supply Erection & Commissioning of additional LT Lines & Diesel Generator at Sawner BCP. For Maharashtra Border Check Post Network Limited MBCPNL/HTA/BPC
/ELE/WO/12-13/1535
Dated 28/05/2012
Rs. 5,92,910 December 2012 Rs. 5,92,910
66. Work order for Supply Erection & Commissioning of additional 33 KV HT line & 33 KV DP Structure with GOD, DO, & LA. at Sawner BCP. For Maharashtra Border Check Post Network Limited MBCPNL/HTA/BPC/
ELE/WO/12-13/1938
Dated 01/11/2012
Rs. 12,28,980 December 2012 Rs. 12,28,980